PORT OF BRISBANE - NEW PORT OFFICE
Start Date:20/03/2009
End Date:TBA
CLIENT: ADCO CONSTRUCTIONS PTY LTD
Extent of Works: Pump, place, finish and cure to - * Subfloor ducts and trenches - slabs & walls * Lift & stair pit walls below GF level * GF Slabs * Columns * Walls * Suspended Slabs * Entry Cap Slab Level 1 * Seat Slabs Level 3 & 5 * Topping to Level 7 * Stairs * Capping Slabs to stairs & lift * External ramp (SOG, supsended, nibs & walls)
|
 |
|
|
|